To trigger a simulation the user selected the “Generate EPC” [button].
 
 
 
Upon completion of simulation the Results tab displays an overview of results. Results are based on the calculation methodology defined within the Gibraltar 2024 NCM modelling guide.
 
Note: In line with Gibraltar 2024 NCM modelling guide, electricity generator is classed in the following forms:
 
With regards to On and Off-site electricity generation, the below text is taken from the Gibraltar Part F (2007) NCM modelling guide:
“Paragraph 112 - When calculating an EPC rating, only the on-site component is taken into account initially. Where off-site generation is also accredited, the Energy Performance Certificate will state the effective rating which would be achieved if the relevant amount of generated electricity were taken into account.”
 
Simulation outputs can be viewed via the Building Compliance > View Results Folder.
 
 
Selection of the “View EPC”, “View Recommendations” and “Supplementary Report” [buttons] launch the EPC reportage documentation. Below is an example of the Energy Performance Certificate (EPC) as part of the Gibraltar Part F (2007) EPC simulation.