Reference SHW Configuration Guidance NECB 2017

While some predefined elements have been provided to the user through the NECB navigator e.g. fuel fired SHW plant in ApacheHVAC, the configuration of the reference SHW system needs to be compiled by the user. The following notes provide guidance on the reference configuration:
 
Table 6.2.2.1 states the equipment performance requirements:
 
 
 
Section 8.4.4.2.(2) states:
 
 
Section 8.4.4.6.(3) states:
  1. One gas fired service water heater shall be used to represent the purchased energy equipment,
  2. Where the proposed buildings purchased energy system is used to heat service water in a heater with a storage tank the service water heater shall have the same storage capacity and,
  3. The total capacity of the service water heaters, relative to the reference building's total service water heating capacity, shall correspond to the ratio of the proposed building's purchased energy capacity divided by its total heating capacity.
 
Section 8.4.4.20 states:
 
  1. Storage capacity
  2. Power input, and
  3. Energy type
 
 
 
  1. the heating capacities of the reference building's service water heating equipment shall match the ratio of the proposed building's service water heating equipment capacity allocation, and
  2. the operating schedule, priority of use and other operational characteristics of the proposed building's use of energy types shall apply.
 
 
 
 
 
  1. constant speed operation, and
having a flow rate and pumping power, in W/(L/s) that is identical to that of the proposed building's circulation pumps.